Available in Sage 50 Quantum Accounting.
Update a Work Ticket
From time to time, you will need to update work tickets with your progress. Follow the steps below to update a work ticket.
- From the Tasks menu, select Work Tickets. The Work Tickets window appears.
- Click the Open button and select the ticket that you want to update and click OK. The selected work ticket information appears in the Work Ticket window.
- Update any of the information that has changed on the work ticket.
- If you have finished or received items in the component list, select the corresponding Finished check box and enter the Act Hours, if you are tracking hours.
- Then, click Save. After you have marked one item in your component list as finished, your work ticket is given a status of In Progress.